Naksha Pass in Patna: Building Plan Fees, Papers, 2026 Rules
Quick answer
From 12 November 2026, a house up to 10 m high needs no approval from the corporation.
- An empanelled architect approves the plan and uploads it. You pay and download the approval.
- Fee: to be notified under the new rules. On 19 November, Automap still showed ₹12 per sq m.
- Above 24 m or 5,000 sq m: the corporation or department decides in 30 days.
But the land's zone and the road in front still decide what you can build.
📑 Jump to a section (7)
Six steps to get a naksha passed in Patna
- Check the land's zone and the road in front. The master plan zone and the road width come first. How to find the zone: Patna Master Plan 2031 explained.
- Pick an empanelled architect or engineer. The portal's "Find a Technical Person" page lists the panel. The plan carries their signature and yours.
- Get the land papers ready. Sale deed, mutation and the land rent receipt come first. Full list below.
- The plan goes on the portal. The architect draws it in AutoCAD, turns it into the portal's own file (.apz) and uploads it.
- Pay online. The portal shows the total fee before final submission. Payment is online only.
- Approval. Up to 10 m, an empanelled architect approves it. Up to 24 m, a second empanelled architect approves it. Above that, the corporation or the department checks. Details below.
The portal covers only the Patna Municipal Corporation area. You can also follow your file there under "View your Applications Status".
Source: Patna Municipal Corporation's Automap portal (FAQ and guidelines) and the Bihar Building Byelaws 2026.
Which risk class is your house in?
The class decides who approves the plan. For residential buildings:
| Condition | Low risk | Moderate risk | High risk |
|---|---|---|---|
| Height | Up to 10 m (about G+2) | Above 10 m, up to 24 m | Above 24 m |
| Built-up area (all floors) | Up to 2,500 sq m | 2,500–5,000 sq m | Above 5,000 sq m |
If even one condition falls in a higher class, the whole building goes into that class. A family house rarely comes near 2,500 sq m, so its height usually decides. Shops and offices have the same limits, if the business is not hazardous.
Low risk: self-certification.
- An empanelled architect or engineer approves the plan and uploads it on the portal.
- You pay the fee and download the approval certificate. The corporation doesn't approve it separately.
- No fire NOC is needed. The plan must still have basic fire safety, and a fire audit can come later.
- A permit obtained with false information can be cancelled. The building can then be sealed.
Moderate risk: a second architect approves. An empanelled architect approves the plan online. The person who drew the map can't approve it.
High risk: the corporation or department checks.
- All objections come together within 15 days. The site inspection happens in the same period.
- You correct the plan and resubmit within 7 days. The decision follows within 7 days.
- No decision within 30 days of the application? The plan counts as approved.
- A refusal must state its reasons. You can appeal to the tribunal.
Source: Bihar Building Byelaws 2026 (Bihar Gazette, 12 November 2026).
What is the naksha pass fee in Patna?
The new byelaws don't fix an amount. Fees follow the rates the authority notifies. We found no new fee list up to 19 November 2026.
Until then, Automap's fee page still lists this building permit fee. It is charged on the total built-up area, all floors together.
| Building height | Residential (₹ per sq m) | Non-residential (shops, offices) |
|---|---|---|
| Up to 10 m | ₹12 | ₹24 |
| Up to 15 m | ₹18 | ₹36 |
| Above 15 m | ₹25 | ₹50 |
On top of it:
- Scrutiny fee: the new byelaws name it; the amount is to be notified.
- Labour cess: 1% of the construction cost, worked out from the Central PWD plinth area rates.
- Pasting/scanning fee: ₹100, for the record.
- Shelter fund: on plots of 500 sq m or more, or more than 8 flats.
An example at the portal rate: a G+2 house on 2 kattha (about 253 sq m). It has 400 sq m built up across three floors. Permit fee: 400 × ₹12 = ₹4,800. Add the scrutiny fee, ₹100 and labour cess. Pay what the portal shows before you submit.
Revising an approved plan within 3 years, with no extra area: a quarter of the permit fee. To turn kattha into square metres, use the kattha converter.
Source: Automap fee page, checked on 19 November 2026.
What documents does naksha pass need?
Land papers:
- Sale deed (kewala) or khatiyan. For inherited khatiyan land, the partition papers too.
- Mutation order or LPC. See dakhil-kharij online.
- Latest land rent (malguzari) receipt: lagan receipt online. In the city, the holding tax receipt too: property tax receipt.
- A registered development agreement, if a builder is building with you.
Affidavits and technical papers:
- Affidavits: no litigation and peaceful possession, road widening, land ceiling.
- Structural certificate (including earthquake safety) and a supervision certificate.
NOCs, where they apply:
- Airports Authority: in height-restricted areas near the airport.
- Fire: not for a self-certified building. Bigger buildings attach a certificate from an empanelled fire consultant or the fire officer.
- Archaeology (ASI), forest department: if they apply. Environment: above 20,000 sq m built up.
If a paper is missing, the application is sent back to you. You fix it and submit again.
Source: Automap portal, "What are the documents required", and the Bihar Building Byelaws 2026.
After approval: 5 + 5 year validity and OC
- High-risk sites: keep the approved drawings on display during work. Put the owner's and site supervisor's names at the gate.
- Valid for 5 years: report completion within this time. If you can't, revalidate before it lapses. On payment, you get 5 more years at once. Not done in 10 years? Apply afresh.
- Low and moderate risk: no occupancy certificate (OC) from the corporation is needed. A licensed architect issues a completion-cum-occupancy certificate online.
- High risk: officials check within 7 days of your completion notice. The completion certificate comes within 30 days, then the OC within 15. If either is late, it counts as issued and can be downloaded.
Source: Bihar Building Byelaws 2026 (Bihar Gazette, 12 November 2026).
Bihar Building Byelaws 2026: what changed for a house
The new byelaws were published in the Bihar Gazette on 12 November 2026 and apply from that day. They replace the 2014 byelaws and all their amendments.
- Old permits stay valid. A permit issued before 12 November counts under the new rules. If it lapsed before work began, the new rules apply.
- Built without a permit? If the building meets the new rules, you can apply for a permit. The state will notify the fee.
- No setback on small plots. A single house up to 10 m needs none, if the plot is up to 20 m wide or 20 m deep.
- Floor area and height. Every plot gets a base FAR of 3.0, and more can be bought. Height has no general cap, except near airports and monuments.
- Rainwater harvesting. Plots of 100 sq m or more must show it in the plan.
- The master plan comes first. Where its rules differ from the byelaws, the master plan wins.
Source: Bihar Building Byelaws 2026 (Bihar Gazette, 12 November 2026).
What should you do?
- Check the zone and the road before you buy the plot. Plans get stuck where the land's zone doesn't fit.
- Get mutation and the rent receipt in your name first. The file doesn't move without them.
- Ask your architect in writing: which risk class, who approves, and the total fee.
- Pay only online on the portal. Never hand cash to anyone "for naksha pass".
- Keep the approval, the completion and occupancy certificate and receipts safe. Buyers and banks ask for them later.
Naksha pass in Patna: FAQs
Do I need naksha pass even for a small house on 1 or 2 kattha?
Yes. A new house, rebuilding or a new floor needs a plan on the portal. A house up to 10 m just takes the self-certified route. Only internal changes that don't touch the structure or fire safety need no permission.
Where is naksha pass done in Danapur, Phulwari or Khagaul?
Automap covers the Patna Municipal Corporation area. Outside it, ask your own municipal body or planning authority. The same Bihar Building Byelaws 2026 apply in every municipal body and planning area. They don't apply in a cantonment area, such as Danapur Cantonment. Ask the Cantonment Board there.
I want to add a floor to my existing house. What do I do?
The new floor needs a plan too, and the portal works out the fee. If the house goes above 10 m, it becomes moderate risk. A second empanelled architect must then approve it.
What if the house was built a little different from the approved plan?
Small excesses can be condoned: up to 10% in side and rear setbacks, FAR and height. You pay a fee, and the new rates are still to be notified. Automap's list still shows ₹2,000 per sq m (compounding) and ₹10,000 per sq m (condonation) for homes. Anything beyond the limits must be demolished. So build exactly to the plan.
All articles in this series (15): Patna Master Plan 2031 & Patliputra Township
- Patliputra Township Patna: Registry Open, Construction Still Barred
- Patliputra Township Village List (2026): Is Your Village Included?
- Patna Master Plan 2031 PDF and Zones Explained for Plot Buyers
- Can You Build a House in Patna's Green Belt? Master Plan 2031 Rules
- Patna Master Plan 80 m & 60 m Roads: Village-wise Route 2026
- Patna Metro Route, Stations & Status 2026: Plot Buyer's Guide
- Patna Ring Road & Bypass 2026: Status, Route, Plot Check
- Buying a Plot in Bihta, Naubatpur, Fatuha or Punpun? Patna 2026
- Greater Patna Area 2026: Blocks List, Map & Master Plan
- Patna Flood-Prone Areas: Check a Plot for Flood, Buffer, Earthquake
- Naksha Pass in Patna: Building Plan Fees, Papers, 2026 Rules
- Land Needed for a Petrol Pump in Bihar: Size in Kattha & Decimal
- Shop in a Residential House in Patna: Master Plan Mixed-Use Rules
- Patna Road Widening List 2026: Which Roads, How Wide
- Patna Planning Area Village List: All 575 Villages, Block-wise
The rules before 12 November 2026 (now repealed)
- Low risk was a plot up to 300 sq m and a house up to 10 m. A house with more than 8 flats was high risk.
- Low and moderate risk went through "trust and verify". The corporation inspected at least 15% of such sites a year.
- Scrutiny fee: ₹1,000 for low, ₹5,000 for moderate and ₹10,000 for high risk.
- Work started after a notice in Form X. No inspection within 14 days meant no objection.
- A permit was valid for 5 years, plus 2 on payment. Condonation allowed 5% extra FAR and 5% height, at most 0.90 m.
Latest news on this topic
From our weekly news. The figures in this guide change only when an official order comes out.
🕘 What changed in this article
- 20 November 2026: Rewritten for Bihar's new building rules (Bihar Building Byelaws 2026), in force from 12 November 2026. A house up to 10 m (about 33 ft) high no longer needs the corporation's approval. An architect on the official panel passes the plan online. The approval lasts 5 years and can be extended by 5 more. Who gives the OC has changed too. The old rules are kept in a box lower down.
Sources
- Patna Municipal Corporation, Automap (Building Plan Approval System): What is AutoMap — automap.bihar.gov.in; fees (How much is the fees) — FAQ6; documents — FAQ5; site inspection — FAQ4; .apz file guidelines — PDF. Checked on 19.11.2026: the fee page still lists the permit fee (₹12/₹18/₹25 residential), the ₹100 pasting fee, labour cess, shelter fund, revision at a quarter fee, and compounding ₹2,000 / condonation ₹10,000 per sq m.
- Bihar Building Byelaws 2026, Urban Development & Housing Department notification of 12.11.2026 (no. …-03/2026-11445), Bihar Gazette (Extraordinary) No. 1417, 12.11.2026 (Hindi pp. 1–79, English pp. 80–147): byelaws 1(2), 1(4) (not in cantonment areas), 1(6) (master plan prevails), 1(7) (in force on publication); Applicability and Deemed Permission (old permits; 30 days); 5A–5C, Table 1 (exempt works, self-certification, fire NOC); 6(6)–6(7) (fire plan, NOCs); 8 (fees as notified); 9(1)–9(4), Table 3–4 (risk classes, approval routes: corporation or department for high risk, 15+7+7 days, appeal); 10 (5 + 5 years, 10 years); 11–14 (site display, inspection, completion, OC; 14(1) completion-cum-occupancy from a licensed architect); 24 (rainwater harvesting); 28(3) (no setback); 29 (base FAR 3.0); 30 (height); 33 (compounding, condonation up to 10%); 35 (repeal of the 2014 byelaws and amendments; permit for earlier construction) — PDF
- Rules before 12.11.2026, now repealed (the box above): Bihar Building Byelaws, 2014 (English, December 2014) — PDF (Automap); Bihar Building (Amendment) Byelaws, 2022 (notification no. 645): 8(1) risk matrix, 9 (5+2 years), 10 (Form X, 14 days) — PDF (PMAA); Bihar Gazette (Extraordinary) No. 462, 12.05.2026: 8(1) (more than 8 flats = high risk), 8(2) (trust and verify, ₹1,000/₹5,000, 15% inspections), 8(4)(1) (₹10,000) — PDF
- 1 kattha = 126.51 sq m (note on the Automap fee page). At 1,361.25 sq ft a kattha, it works out to 126.46 sq m.
General information from official sources, checked on 20 November 2026. Rules change — confirm with the registry or circle office before paying.