RERA Bihar Project Check: How to Verify a Patna Project 2026

Quick answer

Search the project on rera.bihar.gov.in → Projects → Search Project, then open its BRERAP certificate.

  • Note the date the registration ends.
  • Read the quarterly progress reports: work done, flats booked, money collected and spent, photos, cases.
  • Since 21 September 2026, pay only into the account named "Promoter – Project – RERA Master Account".

But "RERA approved" alone proves little. A registered project can still be years late.

📑 Jump to a section (8)
  1. How to check a project on RERA Bihar (step by…
  2. Read the registration certificate (Form 'C')
  3. What to read on the project page
  4. Quarterly progress report (QPR): is the project…
  5. New since September 2026: pay only into the…
  6. Check the builder, the broker and the site board
  7. Lapsed, revoked, extended: what the status means
  8. Questions & answers

How to check a project on RERA Bihar (step by step)

It takes about 15 minutes. The screens below are as the portal showed them on 25 October 2026.

  1. Open rera.bihar.gov.in → Projects → Search Project.
  2. In Select Category, pick Registration No, Project Name, Promoter Name, Builder Name/PAN No., location or a type such as Plotted Development. Type and click Search Now.
  3. The result shows the promoter, the BRERAP… registration number and the address with block, mauja and plot number. "Location of Project" shows it on a map.
  4. Click the BRERAP number: the project's registration certificate (Form 'C') opens as a PDF.
  5. Click the QR code next to the project: this opens the project's full public page. It has documents and quarterly progress reports.
  6. Only have a number from a brochure? Projects → Verify Project Registration checks just the number.
  7. Nothing found? Look in Rejected Projects List and Defaulter List before you decide anything.

Tip: search the builder's PAN too. You'll see all its Bihar projects; check the old ones for delays.

Read the registration certificate (Form 'C')

Three lines matter:

Line in the certificateWhat to check
"The registration shall be valid for a period of … ending with …"This is the completion date the builder declared. If your possession date in the agreement is later, ask why. If the date has already passed, the registration has lapsed unless an extension was granted.
Land table: district, circle, halka, mauja, plot, area (in decimal)Match it with the jamabandi and khatiyan of the same plot. The area is in decimal (dismil): 1 decimal ≈ 40.47 sq m (435.6 sq ft).
Bank and account numbers (Master, Project, Promoter account)Pay only into the Master Account listed here (see below).

What to read on the project page

The parts of the project page worth your time:

Section on the pageWhat to checkRed flag
Project InformationProject type, status, start and end date, total land area, number of phasesEnd date already past; "Reason for delayed" filled in
Project Location DetailsKhesra/plot no., circle, mauja, the four boundariesPlot number or boundaries different from the sale papers you are shown
Land documentsMutation slip, sale deed/khatiyan, online jamabandi, LPC, revenue receipt, non-encumbrance certificate, development agreementDocuments missing, or jamabandi in a different name with no development agreement
Sanctioned map"Approved by" (which authority), date and period of approval of the map; sanctioned plan and layout PDFsMap validity ends before the project end date; floors built beyond the sanctioned number
Building detailsNumber of flats by type, carpet area, balcony area, sanctioned vs permissible FARCarpet area on the portal smaller than what you are told
Proforma documentsAgreement for sale, allotment letter, conveyance deedYour agreement differs from the portal's
Promoter detailsPartners/directors, previous projects (last 5 years), registration in other states and whether it was revoked"Revoked: Yes" or a history of delayed projects

Since 2026, the builder must file the current online jamabandi with the application. The revenue receipt and non-encumbrance certificate must be no older than the previous financial year. The map permit letter goes in too. Open these papers: it is the quickest free land-paper check you'll get. What each paper means: jamabandi, khatiyan and LPC online and the encumbrance certificate guide.

Quarterly progress report (QPR): is the project really moving?

Every registered builder must upload a Quarterly Progress Report (Form 7) within 30 days after each quarter ends. The project page has one link per quarter. Each report shows:

  • Work done: % complete for each stage (plinth, slabs, walls, lifts, roads, drains) and the overall %, with geo-tagged, dated site photos.
  • Bookings and money: flats booked (promoter's and landowner's share separately), cancellations, and money collected and spent.
  • Validity and approvals: registration and map valid up to, any extension, and fire, environment and airport NOCs.
  • Track record and cases: the builder's late, lapsed or revoked projects, penalties, and legal or recovery (PDR) cases.

How to read it: open the last 3–4 quarters side by side. If the overall % hardly moves, or photos or recent quarters are missing, the project is likely behind.

Source: Bihar RERA (General) Regulations 2026 and the QPR FAQ (full list at the bottom).

New since September 2026: pay only into the RERA Master Account

After a Supreme Court judgment of 12 September 2025, RERA Bihar issued Office Order 288 (21 September 2026). Every registered project now has three accounts.

  • RERA Master Account: the only account for buyers' payments, named "Name of Promoter – Project Name – RERA Master Account". It must be printed on the allotment letter, agreement, demand notices and payment schedules.
  • RERA Project Account: at least 70% of every payment moves here automatically the same business day. Money comes out only against architect, engineer and CA certificates of work done (Forms 1, 2 and 3).
  • RERA Promoter Account: gets the remaining 30% or less.

What this means for you: match the demand letter's account number with the Master Account on the RERA certificate. Don't pay cash, or into a director's or "sister company" account. Money that skips the Master Account loses this protection.

Check the builder, the broker and the site board

  • Defaulter List: under Projects → Defaulter List (Revoked, Lapsed, Suo-Motu, Execution, PDR). It names builders with revoked or lapsed projects, recovery (PDR) cases, or who ignored RERA's orders.
  • Orders: search the builder's name under Complaints → Order/Judgments. Already booked and the builder is late? See how to file a RERA Bihar complaint.
  • Broker: anyone who sells flats or plots in a registered project for a fee must be registered. That includes property dealers. Check them under Agents → Registered Real Estate Agent by name, registration number or district.
  • Site board: every registered project must have a board of at least 5 ft × 4 ft. It shows the registration number and RERA's QR code. A plot project's board also shows the plot, khata and thana numbers and the layout over the revenue map. Scan the QR code at the site and check it opens the same project.

Lapsed, revoked, extended: what the status means

StatusWhat it meansFor a new buyer
Registered, within validityNormalGo ahead with the other checks
Extension grantedCompletion date moved: up to 1 year in total and never a right; special cases not beyond the map's validityCheck why, the work left in the QPR, and the map's validity
LapsedThe completion date passed without an extensionDon't book a new flat until RERA allows the project to continue
RevokedRERA cancelled the registration for default, approval violations, unfair practice or fraudDon't book
RejectedThe application was refusedThe builder can't sell; don't book

Which projects in Patna must be registered with RERA?

  • Size: more than 500 sq m of land (about 0.12 acre), or more than 8 apartments in all phases together.
  • Plots too: a plot colony on more than 500 sq m needs RERA registration just like flats. The portal calls it "Plotted Development".
  • Inside the planning area: the rule applies to projects in a planning area. The Patna Planning Area covers 1,167.04 sq km: 575 revenue villages in 13 blocks, plus 6 towns. Outside it, RERA can still order a builder to register. List: Planning Area → List of Planning Area - Bihar.
  • No registration, no selling: until it is registered, the builder can't advertise, book or sell. Every advertisement must print the RERA registration number and the RERA website.

Source: RERA Act 2016 and RERA Bihar FAQ (full list at the bottom).

What should you do? (our advice)

  • RERA first, site visit second.
  • Read the last four QPRs, not the brochure.
  • Match three things: the plot number on RERA, on the jamabandi and in your agreement.
  • Pay only into the RERA Master Account, by bank transfer, and keep every receipt.
  • Living outside Patna? Check the QPR photos every quarter, and have someone you trust scan the site board's QR code.
  • Then the rest of the flat checks: the 10% booking rule, carpet area, OC and possession are in our Patna flat buying checklist.

RERA Bihar project check: frequently asked questions

  1. The project isn't on RERA. What should I do?

    If it should be registered (over 500 sq m or 8 flats, in a planning area), don't book. Report it under Report Unregistered Project; RERA Bihar keeps your identity confidential. Selling without registration can draw a fine of up to 10% of the project cost. If it truly needs no registration, RERA won't protect you. Check the papers yourself with our plot buying guide and fraud guide.

  2. I'm buying a flat from the landowner's share. What should I check?

    The builder must file a memorandum on RERA showing which flats are the landowner's. Check that your flat is on that list. If the title turns out to be defective, the builder and landowner are jointly liable for compensation.

  3. The project is built in phases. Is one registration enough?

    No. Every phase needs its own registration, with its own BRERAP number and end date.

  4. The builder's company changed its name. How do I see its old projects?

    The promoter search shows "Previous Names". Search both names, including on the Defaulter List.

Checked on the RERA Bihar portal and its rules on 25 October 2026. Rules can change; check again before you pay.

Next step Flat Buying Checklist for Patna 2026: From RERA to Possession RERA is one check. Here is the full list before you book a flat. Read next →
All articles in this series (21): Patna Property Buyer Guide
  1. Buying Property in Patna from Outside: NRI & Migrant Guide 2026
  2. Flat Buying Checklist for Patna 2026: From RERA to Possession
  3. RERA Bihar Project Check: How to Verify a Patna Project 2026
  4. Registry Charges in Patna 2026: 7% + 2% for Land and Flat
  5. Land Registry Process in Patna 2026: Documents + 10 Steps
  6. Dakhil-Kharij (Mutation) Online in Patna: Papers, Time, Status
  7. How to Check Jamabandi, Khatiyan and LPC Online in Patna (2026)
  8. Power of Attorney in Bihar: Patna Property Guide 2026
  9. Land Fraud in Patna: 8 Common Property Scams and How to Avoid Them
  10. RERA Bihar Complaint Against Builder: Patna Delay Guide 2026
  11. Ancestral Land Partition in Patna: Vanshavali, Deed & Mutation
  12. Bihar Land Conversion Repealed: Building on Farmland in Patna (2026)
  13. Encumbrance Certificate Bihar: Check Loans & Cases on Patna Land (2026)
  14. Kewala Copy Bihar: Get a Certified Sale Deed Copy (Patna 2026)
  15. Bihar Rasid Online: Pay Lagan, Get Land Rent Receipt (Patna 2026)
  16. Bihar Land Survey 2026: Form 2, Last Date and Status (Patna)
  17. Flat or Plot: Which Is Better in Patna? An 8-Point Comparison
  18. Home Loan in Patna: Papers, PMAY Subsidy and the Govt Employee Route
  19. Parimarjan Plus Bihar: Correct Your Jamabandi Online (Patna 2026)
  20. Khanapuri Parcha Bihar: Download, Check, Object (Patna 2026)
  21. Property Papers Lost? What to Do in Patna to Get Each One Back (2026)
Sources
  • Real Estate (Regulation and Development) Act, 2016: Sections 2(zm), 2(zn), 3, 5, 6, 7, 9, 11, 59 — PDF (rera.bihar.gov.in)
  • Bihar Real Estate Regulatory Authority (General) Regulations, 2026, Notification No. RERA/Regulation/61/2026-1027, 28 Aug 2026, Bihar Gazette (Extraordinary) No. 1079, 7 Sep 2026: Regulations 4, 6, 8, 9, 10, 11 (English text, p. 48–56) — PDF
  • RERA Bihar Office Order No. 288, 21 Sep 2026: SOP for project bank accounts under Section 4(2)(l)(D), p. 1–3 — PDF
  • RERA Bihar FAQ (Q1, Q32, Q33) and QPR FAQ — FAQ PDF, QPR FAQ PDF
  • RERA Bihar portal pages: Search Project, Verify Project Registration, Rejected Projects List, Defaulter List, Registered Real Estate Agent, Report Unregistered Project, project page and QPR (Form 7) — rera.bihar.gov.in, checked 25 Oct 2026
  • Patna Master Plan 2031 report, p. 22–23 (Patna Planning Area: 1,167.04 sq km, 13 blocks, 575 villages, 6 urban bodies)

General information from official sources, checked on 28 October 2026. Rules change — confirm with the registry or circle office before paying.

Prem Parkash Yadav

36+ years in the Indian Air Force, and alongside it 20+ years of hands-on land experience in Patna.

About Prem ji →
Add PP Properties as a preferred source on Google
WhatsApp Prem ji — Free Advice